REFURBISHMENT WITHIN TIME FRAME AND BUDGET

EDINBURGH

This dated shopping centre had not been refurbished since it was built

 

Challenges:

Gyle Shopping Centre on the outskirts of Edinburgh had not been refurbished since it was originally constructed in 1994 and as such had an extremely dated appearance which was hampering leasing and asset management efforts

Strategy:

A highly respected market leading design team was assembled and formally appointed. Ellandi engaged directly with the two anchor tenants (M&S and Morrisons) whose legal agreement was required to deliver the project
The project had to be completed so as not to interfere with the crucial pre-Christmas trade period

Solutions:

Project completed on-time with a challenging 22 week delivery period and within the £2.5m budget
The successful delivery then directly led to a high-profile letting to JD Sports to coincide with project completion